Wixams station: the smaller build has stopped

Network Rail says the smaller Wixams station has stopped and a four-platform station is being designed. Main work is not expected to restart until 2027. No opening date is published.

Updated

Network Rail’s current account

Network Rail’s Wixams page, checked on 13 November 2026, says a previous development for a smaller station has been brought to a close, and that it is discussing a larger station with the Department for Transport, the local council and other stakeholders. It says it is leading development of a new four-platform station so that workers and visitors can travel to Universal United Kingdom Resort, and so that residents benefit as well.

On the effect of that change, the page says the work originally begun for the smaller station has been brought to a safe and controlled stop, designs for the larger station are being developed, site survey work is expected in 2026, and main work is not expected to restart until 2027. It says residents will be written to before disruptive work. It does not publish a station opening date or a train timetable.

The same page describes the resort as a theme park with several themed lands, a 500-room hotel, and retail, dining and entertainment. That matches the description on Universal’s own project site.

Why an older council page is easy to misread

Bedford Borough Council’s Wixams Station FAQ, still online on 13 November 2026, says the council commissioned Network Rail to deliver the station, that works commenced in September 2024, and that the entry-into-service date was anticipated to be the second half of 2026, before the Universal announcement. A later answer on the same page says construction began in autumn 2024.

The FAQ also says Wixams is independent of East West Rail. It does not say that the smaller scheme has been stopped, and it does not mention the four-platform redesign or a 2027 restart. Anyone using that FAQ as the current programme will get the pre-Universal timetable. Network Rail’s project page is the one that describes the scheme as it stands.

The getting-around guide on this site explains Kempston Hardwick and the Marston Vale line. It does not say that the smaller Wixams works have stopped. This note is that missing update. The practical stop beside the site today is still Kempston Hardwick, with the access limits in the Manor Road note.

How this sits with the resort

Universal’s project site says the project will help deliver an expanded Wixams railway station and direct slip roads from the A421, among other local road improvements. Bedford Borough Council’s resort page says the same direction of travel: works on the resort started in 2026, with opening planned for 2031.

On 12 November 2026 the BBC reported that the Department for Transport had pointed to investment in the new Wixams station and three new A421 slip roads. The same article’s caption says work at Wixams had started but has stopped. A campaign to reopen the old Bedford to Northampton line, and the department’s refusal, is set out in that guide.

None of these sources gives a date when passengers will be able to board a train at Wixams. Until Network Rail publishes one, a commute plan that depends on Wixams being open in 2026 is using the old council FAQ, not the current project page.

Worth knowing. East West Rail’s proposed station for the resort is a different scheme, at a new Stewartby, on the Marston Vale line. It is not the Wixams station on the Midland Main Line. The council FAQ says the two are independent.

Sources

Check these rather than taking our word for it.

This guide is general local information, not professional advice. We are independent and not connected to Universal. Costs and figures are indicative and change.

Common questions

When does Wixams station open?
Network Rail’s project page, checked on 13 November 2026, does not give an opening date. It says main work on the larger station is not expected to restart until 2027. The council FAQ’s “second half of 2026” line is the timetable from before the Universal announcement.
Is the station still a two-platform local halt?
Network Rail says the smaller station development has been closed and that it is developing a four-platform station for residents, workers and visitors to the resort. The final design is not published on that page.
Can I use Wixams to get to the site now?
No. There is no open station there. Kempston Hardwick, on the Marston Vale line, is the existing stop beside the site, and Manor Road access to it is restricted until 27 November 2026.